A customer in Spicer, Minnesota, contacted Duininck to replace a rough gravel driveway with a paved surface. Crews from grading, paving, aggregate, and the truck fleet worked together to complete the residential project.
The property was a recent build, and initial driveway work had been completed by another contractor. When the crew arrived, they determined that additional gravel from the Eagle Lake pit was needed to properly prepare the base. Dispatch coordinated additional trucking support to deliver the materials efficiently.
The project required 200 tons of Class 5 aggregate base, 120 tons of wearing course asphalt hot mix, and topsoil to complete the driveway.
“Design was a bit of an issue because we were adding on to an existing driveway. On paper it might look great, but when you’re actually trying to do what you want, like back your boat into a shed, it might not work as well as you’d think. We can fix those issues before we even start.”
-Lucas, Business Development – Private