The Duininck paving crew completed improvements on Civic Center Drive in Willmar, Minnesota, while limiting traffic disruption to just ten days. The project included asphalt patching, milling, paving, and pavement markings along a two-mile section of roadway that had begun to break apart and no longer held up to traffic.
Crews excavated and patched back 7.5 inches along the shoulder of the road for more than 4,000 feet. After patching was complete, the team began the overlay process.